General arrangement. | First muon event. |
KamLAND overall scheme: pdf
Released engineering drawings and specifications (Z-axis system): 21F9226 SYSTEM CABLING SCHEMATIC 21F9006 GENERAL UTILITY ARRANGEMENT, PLAN 21F9016 GENERAL UTILITY ARRANGEMENT, ELEVATION 21F9176 Z-AXIS SYSTEM ASSY 21F9074 GASKET, M5A 21F9066 M5A FLANGE WELDING 21F9054 M5A FLANGE MACHINING 21F9193 GASKET, M5B 21F9086 SPOOL, M5B 21F9106 SPOOL, M5C 21F9114 SPOOL, M5D 21F9146 ENVELOPE, Z-AXIS GLOVE BOX __M938 SYSTEMS MONITORING GLOVE BOX SPEC 21F9216 LED INSTALLATION 21F9202 LED CAPSULE ASSY 21F9152 HOUSING, LED CAPSULE 21F9161 LENS, LED CAPSULE __M936 LED WIRE PREPARATION SPEC __M937 LED POTTING PROCEDURE SPEC 21F9044 BRACKET, LED 21F9023 ELECTRONICS HUT __M939 ELECTRONICS HUT PROCUREMENT SPEC